Frequency fluctuations have occurred in the energy system, causing the relay protection of major manufacturers to trip, said Deputy Minister of Territorial Administration and Infrastructure Hakob Vardanyan to Radiolur. Initially, the fifth block of the Hrazdan Thermal Power Plant was disconnected, followed by the Yerevan Thermal Power Plant and then the Yerevan HPP.
At one point, only the Vorotan cascade was operational, and we were importing electricity from Iran as a result of the energy crisis, Vardanyan explained.
Currently, restoration work is ongoing, as are the frequency fluctuations. “I cannot specify a time for when the system will be restored; the electricity supply for the Sevan-Hrazdan cascade has been restored,” Hakob Vardanyan stated.
In Yerevan HPP, water has been drained, and efforts are underway to quickly restore it to reconnect to the grid. It will take at least four to five hours. Work is currently underway with Georgia to ensure additional energy supply from there.
Նմանատիպ հոդվածներ
Attention: Emergency in Energy System, Deputy Prime Minister
Currently, we are experiencing an emergency in the energy system. The Yerevan Thermal Power Plant and the 5th block of t...
Manvel Grigoryan's grandson named Manvel drafted into the army
NEWS.am has learned that days ago, the former head of the Yerkrapah Volunteer Union and currently incarcerated general M...
A New Bus Launching in Yerevan
A new bus is being launched in Yerevan as part of a trial operation. This was announced by Yerevan City Council member A...
Extraordinary Incident in Yerevan: Businessman Manvel Ghazaryan of ‘Vedi Alko’ and His Two Sons Detained
According to SHAMSHYAN.com, today, on July 7, officers from the Central Police Department's Criminal Investigation Divis...